UPDATES regarding the Main Street Bridge in downtown Dayton:

 

All,

 

Our contractor for the SR48 over Great Miami River Bridge project is approaching the demo stage of the existing bridge where he will need to completely close the bridge.   He is expected to need 3 weekend closures to completely remove the beams from the Phase 1 section of the bridge; the weekends starting 5/18, 6/1,  and 6/8.   The weekend closures will be from 8pm Friday to 6am Monday.

 

If you have any questions or concerns please don’ t hesitate to contact me.

 

Thanks,

 

Todd Schafer

Transporation Engineer
ODOT District 7 Construction
1001 St. Mary’s Avenue, Sidney, Ohio 45365

(p):  937.312.3874; (m):  937.538.0287
transportation.ohio.gov

 

Description: http://portal.dot.state.oh.us/Divisions/Communications/ODOT%20Icons%20and%20Images%20internal/Ohio%20Department%20of%20Transportation%20-%20New%20Green.emf